|
Date |
Author |
Record |
|
2005-09-04 |
mS |
we now start work at 5:45 because the sun is rising later each morning. We finish at 1:30pm. [Input: P904MS.j]
|
|
2006-09-21 |
mS |
we have changed our work week and will now work from Monday to Saturday and we will have Sunday off. [Input: Q916MS.j]
|
|
2006-09-22 |
mS |
we had no method for removing dirt but tomorrow Muhammad Omo will move two shafats and we will have one large one to move the dirt from a lower level with fewer people. [Input: Q916MS.j]
|
|
2006-09-23 |
mS |
we moved the clocks back one hour last night and now begin work at 5am because it is light. [Input: Q916MS.j]
|
|
2006-09-25 |
mS |
Ramadan has started and we will end work in the field at 11:45 today. The workmen asked not to have a break for breakfast since they are not eating. Beginning tomorrow, we will work straight through from 5:00 to 11:00. [Input: Q916MS.j]
|
|
2006-09-26 |
mS |
the workmen will work from 5am to 11am with only one 15 minute break for those who are not fasting during Ramadan. Several also left to help Muhammed Omo move shafats in other areas. [Input: Q926MS.j]
|
|
2006-09-29 |
mS |
the shafat does not work any longer because the accumulations we are digging are dense and damp and tend to clog the shafat. We will get a couple more workmen to help remove the dirt. [Input: Q926MS.j]
|
|
2007-07-16 |
ms |
mS arrived at the site and set up to work. The staff is working on Loci. [Input: R724MS.j]
|
|
2007-07-18 |
ms |
mS spent the day working on a Freehand project to highlight loci one at a time so they can be seen more easily in the browser. [Input: R724MS.j]
|
|
2007-07-19 |
ms |
started the cycle covering items. lH arrived and will work in J1 doing editing of the books. [Input: R724MS.j]
|
|
2007-07-20 |
ms |
mS and lH continued editing the items and q-items. [Input: R724MS.j]
|
|
2007-07-23 |
ms |
We began the module on plots. [Input: R724MS.j]
|
|
2007-07-24 |
ms |
very little work was done on the plots because of the computer issues. [Input: R724MS.j]
|